What Fire Rated Drywall Installation Involves
Reading the Assembly Listing on the Drawings
- The listing is real and current. Check the exact design number, not just "1-hour wall."
- The listing matches the specified products. A listing written around one manufacturer's board doesn't automatically cover another's.
- The wall runs where it must. Fire separations generally have to be continuous to the underside of the floor or roof deck above, not just to the ceiling grid.
What the Inspector Checks on Site
- Board type stamped on the back of each sheet, matching the listing
- Correct stud gauge and spacing
- Correct number of layers, with joints staggered between layers where required
- Fastener type and spacing
- Continuity to the deck, with no unsealed gaps
- Penetrations and joints sealed with tested firestop systems
- Identification of the separation above the ceiling, where the owner or municipality requires it
1-Hour vs 2-Hour Fire Separation Assemblies
| Typical 1-hour wall | Typical 2-hour wall | |
|---|---|---|
| Framing | Non-load-bearing steel studs, often 3-5/8" at 16" or 24" on centre | Same, or as the listing requires |
| Board | One layer 5/8" Type X each side | Two layers 5/8" Type X each side, or a Type C build-up |
| Joints | Taped and finished | Face layer taped and finished; base layer joints staggered from face layer |
| Fasteners | Type S screws at the spacing in the listing | Separate spacing for base and face layers, per the listing |
| Wall thickness (3-5/8" stud) | About 4-7/8" | About 6-1/8" |
Typical 1-Hour Steel Stud Assembly
Typical 2-Hour Assembly
Where Each Shows Up
- Exit stairs and exit corridors: often 1 to 2 hours, depending on building height and the floor assemblies they connect
- Public corridors serving suites: commonly 45 minutes to 1 hour
- Separations between major occupancies (for example, retail below offices): commonly 1 to 2 hours
- Suite separations and demising walls: where the code requires them, often 1 hour
- Service rooms (electrical, mechanical, storage): ratings set by the room's use
- Ceiling in multi-story buildings (like a basement apartment or a multi-level commercial space): the ceiling drywall is the horizontal fire separation
Type X Drywall for Commercial Projects vs Type C
| Type X | Type C | |
|---|---|---|
| Core | Gypsum with glass fibres | Gypsum with more glass fibre plus heat-expanding additives |
| Typical use | Most 1-hour and 2-hour walls and ceilings | Rated ceilings, some higher-rated or thinner assemblies, shaftwall face layers |
| Cost | Lower | Higher |
| Interchangeable? | Only where the listing allows it | Only where the listing allows it |
Shaftwall Systems for Stairwells, Elevator Cores and Mechanical Chases
- Pressure and deflection: elevator cars move air, so shaft walls are designed for pressure as well as fire, which limits wall heights and stud sizes
- Sequencing: liner panels often have to go in before elevator rails or equipment, so scheduling with the elevator trade matters
- Penetrations: door frames, call buttons and controls all need details that maintain the rating
Firestopping and Acoustic Fire Sealants at Perimeter Joints
- Head of wall: the joint between the top of the wall and the deck above. Floors deflect, so this joint has to allow movement and still seal. It needs a tested head-of-wall joint system paired with the right framing detail. See our guide to slotted deflection track at the head of wall.
- Penetrations: pipes, conduit, ducts and cable bundles through the wall. Each type of penetration needs its own listed system, often an intumescent sealant that expands under heat to close the opening as plastic pipes or insulation burn away.
- Perimeter and bottom joints: gaps at floors, columns and intersecting walls.
Fire-Rated Installation Checklist for GCs
- Every rated wall type on the drawings is tied to a specific listing number
- Submitted products (studs, board, firestop) match those listings
- Any substitution has a listing that covers it, approved in writing
- Rated walls are marked to run to the deck, not the ceiling
- Stud gauge and spacing match the listing
- Board stamps match the specified type (Type X or Type C)
- Layer count, joint offsets and fastener spacing match the listing
- Head-of-wall deflection detail is installed as designed
- Every penetration has a listed firestop system, installed and labelled
- Head-of-wall and perimeter joints are sealed with tested systems
- Joints are taped as the listing requires, including above the ceiling line
- Separations are identified above the ceiling where required
- Photos are taken of each rated wall before it is hidden